Lambeth College’s Clapham campus is being redeveloped to provide new teaching, learning and administrative spaces. South Bank Colleges has appointed Neilcott Construction to deliver the scheme, which includes a new four-storey extension and the refurbishment of Block A.

What is changing

The new extension will replace the former sports hall and provide additional education space for students and staff. The development also includes a dining hall and shop, alongside new cycle parking and other improvements across the site.

Construction update October 2026

Demolition of the former sports hall is now substantially complete, allowing the project to move into the next phase of construction.

Neilcott’s October 2026 update sets out specialist piling works during October and November to create the deep foundations needed to support the new building. This work involves piling rigs, excavators, concrete works and the delivery and removal of construction materials.

A large mobile crane is provisionally planned for selected dates in mid-November 2026 to help erect the tower crane. Temporary traffic management and controlled delivery arrangements may be required during lifting operations. Further details will be provided closer to the dates where necessary.

constructionmontage lc nov2026

What happens next

Subject to progress on site, the following activities are anticipated during November and December 2026:

  • Completion of piling works.
  • Construction of pile caps and ground beams, which form part of the building’s foundations.
  • Installation of below-ground drainage.
  • The start of reinforced concrete works beneath the main building structure.
  • Continued coordination of utilities and site infrastructure.

These stages will prepare the project for work on the main building structure during 2027.

College life during the works

The redevelopment is taking place on a working college campus. Neilcott’s site team is working closely with South Bank Colleges and the wider project team to manage construction safely alongside day-to-day college activity.

Piling can generate higher levels of noise and vibration. Measures to minimise disruption include noise and dust controls, wheel-washing and road cleaning, booked deliveries, controlled construction traffic routes and regular environmental monitoring. Dust, noise and vehicle movements will be monitored throughout the works.

The site is registered with the Considerate Constructors Scheme, which assesses construction sites against its Code of Considerate Practice to help reduce their impact on the local community.

Construction working hours

Construction activities will generally take place within the approved hours:

  • Monday to Friday: 8am to 6pm.
  • Saturday: 8am to 1pm, where required.

Noisy activities will be planned and managed to minimise unnecessary disturbance.

What the new building could look like

The architectural images in the gallery show the proposed extension alongside the existing college buildings here. They are illustrations of the proposed design, rather than photographs of completed work.

Images: Rock Townsend Architects LLP.

Project updates

Further information about the project, including its timetable and any changes affecting students, staff or visitors, will be added to this page as it becomes available.

Questions about construction activity

For questions or comments about the works, contact Neilcott’s Project Manager, Sabin Negru, at This email address is being protected from spambots. You need JavaScript enabled to view it. or on 07497 385352.